[ARCHIVED] Goodale Boulevard Improvements (Lincoln to Grandview)

On Monday September 8 the contractor will begin placing a new storm sewer across Grandview Avenue to connect with the new Goodale line. The installation is expected to take 3 days. One lane of traffic will be maintained in each direction on Grandview Avenue. Delays should be expected. If possible use an alternate route during this time.

Also on Monday September 8 Urlin Avenue will shut down for a period of 14 days to install the underground utilities and to prepare it for paving.

Storm line installation from Broadview to Urlin will continue through September 15.

On Wednesday September 10 the installation of curbs will begin on the section of Goodale between Lincoln and Urlin. Weather permitting the paving of that section will begin September 18.